Methods Of Scheduling
The three methods for project scheduling are:
1.Gantt chart:
2. Critical Path Method (CPM)
Critical
path is a
sequence of critical tasks/activities and is the largest path in the project
network. It gives us the minimum time which is required to complete the whole
project. The activities in the critical path are known as critical activities
and if these activities are delayed then the completion of the whole project is
also delayed.
Rules for designing the Activity-on-Node network diagram:
A
project network should have only one start node
A
project network should have only one end node
A
node has a duration
Node Representation
:
Activity label is the name of the activity represented by that node.
Earliest Start is the date or time at which the
activity can be started at the earliest.
Earliest Finish is the date or time at which the
activity can completed at the earliest.
Latest Start is the date or time at which the
activity can be started at the latest.
Latest Finish is the date or time at which the
activity can be finished at the latest.
Float is equal to the difference between
earliest start and latest start or earliest finish and latest finish.
FORWARD PATH EF=ES+DURATION
BACKWARD PATH LS=LF-DURATION
SLACK= LS-ES
OR
LF-EF
Example:
ACTIVITIES |
PREDECESSOR |
DURATION |
A |
2 |
|
B |
A |
4 |
C |
A |
6 |
D |
B,C |
8 |
E |
C |
1 |
BACKWARD PASS:
Is a technique adopted by organization to analyze and represent the activity in a project.
PERT is a method to evaluate and estimate the time required to complete a task within deadlines.
The main
goal of pert
is to reduce
the cost and
time needed to
complete a project.
PERT
was developed in
1950 by the
U.S navy during
the cold war.
It
is commonly used
in conjunction with
the critical path
method .
PERT
has the potential
to reduce both
the time and
cost required to
complete a project.
STEPS IN
THE PERT PLANNING
PROCESS:
PERT
planning involves the
following steps:
1. Identify the
specific activities.
2. Determine the
sequence of those
activities.
3. Construct a
network diagram.
4. Estimate the
time required for
each activity.
5. Determine the
critical path.
ESTIMATING TIME:
A
distinguishing feature of
PERT is its
ability to deal
with
Uncertainty in activity
completion times .
for each activity,
the model usually
include there time
estimates.
OPTIMISTIC TIME(O): The
shortest time in
which the activity
can be completed.
MOST LIKELY TIME(M): The
completion time having
the highest probability .
PESSIMISTIC TIME(P): The
longest time that
an activity might
require.
DURATION= O+4M+P/6
No comments:
Post a Comment